UMIS Number | BG1846-3.001-0001-C03 |
Project Name | 123 |
Beneficiary | 176001209 222 |
Funding | ERDF, EEA FM ==> Program for Optimizations and Testing |
Date of the Contract/Order | 10.12.2024 |
Start Date | 09.12.2024 |
End Date | 18.07.2025 |
Status of Implementation of the Contract/Order of the Grant | In execution (starting date) |
Location of Performance |
|
Brief description |
два |
Activities |
|
Partners | None |
Contractors | None |
Subcontractors | None |
Members of the Consortium | None |
Notes: * The projected contract value may be lower than the reported one because of any of the following reasons:
** This column represents the amount of costs claimed by the beneficiary |
Indicator 1 | Инди, Measure Unit: %, Base Value: 0.00 , Target amount: 90.00 , Reached amount: 0.00 |
Total Project cost | 25 000 000.00 BGN |
Grant | 21 000 000.00 BGN |
Self amount | 4 000 000.00 BGN |
Total actual amounts paid | 0.00 BGN |
Percentage of EU co-financing | 57.14 % |
None | |
Notes: 1 The quoted value represents the maximum amount of the imposed financial correction. Depending on the performance of the contract, the actual amount of the deducted financial correction may be lower. 2 A financial correction with a zero total value means that it has been canceled as a result of a court judgment. |
There are no tender procedures |
Notes:
All amounts are in Bulgarian lev (BGN) / 1 EUR = 1,95583 BGN