| UMIS Number | PAxis-2.001-0003-C07 |
| Project Name | Test |
| Beneficiary | 121100421 te |
| Funding | ESF, ERDF ==> OP Indicators |
| Date of the Contract/Order | 26.11.2019 |
| Start Date | 01.11.2019 |
| End Date | 28.03.2020 |
| Status of Implementation of the Contract/Order of the Grant | In execution (starting date) |
| Location of Performance |
|
| Brief description |
предложение |
| Activities |
|
| Partners |
|
| Contractors |
|
| Subcontractors | None |
| Members of the Consortium | None |
|
Notes: * The projected contract value may be lower than the reported one because of any of the following reasons:
** This column represents the amount of costs claimed by the beneficiary |
|
| Indicator 1 | Насищане с натрупване, Measure Unit: %, Base Value: 0.70 , Target amount: 0.50 , Reached amount: 0.30 |
| Indicator 2 | Насищане без натрупване, Measure Unit: %, Base Value: 0.70 , Target amount: 0.50 , Reached amount: 0.30 |
| Total Project cost | 5 112.94 EUR |
| Grant | 5 112.94 EUR |
| Self amount | 0.00 EUR |
| Total actual amounts paid | 0.00 EUR |
| Percentage of EU co-financing | 50.00 % |
| None | |
|
Notes: 1 The quoted value represents the maximum amount of the imposed financial correction. Depending on the performance of the contract, the actual amount of the deducted financial correction may be lower. 2 A financial correction with a zero total value means that it has been canceled as a result of a court judgment. |
|
| Procedure 1 |
Subject to due process: Доставка на ваксини - ОП1,
Estimated Amount: 30 147.30
|
| Procedure 2 |
Subject to due process: Закупуване на куче,
Estimated Amount: 2 556.46
|
| Procedure 3 |
Subject to due process: Закупуване на Предмет ,
Estimated Amount: 265 871.78
|
Notes:
All amounts are in euro (EUR) / 1 EUR = 1,95583 BGN