| UMIS Number | BG16M1OP002-1.025-0003-C04 |
| Project Name | Proekt 33 |
| Beneficiary | 000817529 reg |
| Funding | ERDF ==> Environment 2014-2020 |
| Date of the Contract/Order | 24.06.2019 |
| Start Date | 25.06.2019 |
| End Date | 25.07.2020 |
| Status of Implementation of the Contract/Order of the Grant | In execution (starting date) |
| Location of Performance |
|
| Brief description |
Проектът за изменение е изпратен по компетентност за приемане от Министерския съвет. |
| Activities |
|
| Partners |
|
| Contractors |
|
| Subcontractors | None |
| Members of the Consortium | None |
|
Notes: * The projected contract value may be lower than the reported one because of any of the following reasons:
** This column represents the amount of costs claimed by the beneficiary |
|
| Indicator 1 | Water bodies with improved monitoring of the quantitative status, Measure Unit: Брой, Base Value: 0.00 , Target amount: 13.00 , Reached amount: 9.00 |
| Indicator 2 | Увеличение с натрупване върху целева, Measure Unit: EUR, Base Value: 0.00 , Target amount: 1.00 , Reached amount: 0.00 |
| Indicator 3 | Намаление на инциденти без натрупване, Measure Unit: Брой, Base Value: 0.00 , Target amount: 200.00 , Reached amount: 50.00 |
| Indicator 4 | Намаление на инциденти с натрупване върху целева без натрупване при отчитане, Measure Unit: Брой, Base Value: 100.00 , Target amount: 30.00 , Reached amount: 2.00 |
| Indicator 5 | Намаление на инциденти с натрупване при отчитане, Measure Unit: Брой, Base Value: 100.00 , Target amount: 30.00 , Reached amount: 20.00 |
| Indicator 6 | Намаление на инциденти с натрупване, Measure Unit: Брой, Base Value: 100.00 , Target amount: 30.00 , Reached amount: 55.00 |
| Indicator 7 | Additional population served by improved water supply, Measure Unit: лица, Base Value: 0.00 , Target amount: 1.00 , Reached amount: 0.00 |
| Total Project cost | 382 701.96 EUR |
| Grant | 374 776.94 EUR |
| Self amount | 7 925.02 EUR |
| Total actual amounts paid | 0.00 EUR |
| Percentage of EU co-financing | 90.00 % |
| None | |
|
Notes: 1 The quoted value represents the maximum amount of the imposed financial correction. Depending on the performance of the contract, the actual amount of the deducted financial correction may be lower. 2 A financial correction with a zero total value means that it has been canceled as a result of a court judgment. |
|
| Procedure 1 |
Subject to due process: Закупуване на техника,
Estimated Amount: 12 782.30
|
Notes:
All amounts are in euro (EUR) / 1 EUR = 1,95583 BGN