| UMIS Number | BG16RFOP001-1.010-0045-C05 |
| Project Name | Project for educational infrastructure |
| Beneficiary | 000413974 Pleven municipality |
| Funding | ERDF ==> Regions in Growth 2014-2020 |
| Date of the Contract/Order | 10.11.2015 |
| Start Date | 10.11.2015 |
| End Date | 21.04.2018 |
| Status of Implementation of the Contract/Order of the Grant | In execution (starting date) |
| Location of Performance |
|
| Brief description |
Oбщата цел на настоящото проектно предложение е да осигури модерна, здравословна и функционална образователна инфраструктура с високо ниво на енергийна ефективност в общинските училища на територията на града. |
| Activities |
|
| Partners | None |
| Contractors |
|
| Subcontractors | None |
| Members of the Consortium | None |
|
Notes: * The projected contract value may be lower than the reported one because of any of the following reasons:
** This column represents the amount of costs claimed by the beneficiary |
|
| Indicator 1 | Брой на модернизираните образователни институции, Measure Unit: Брой, Base Value: 0.00 , Target amount: 4.00 , Reached amount: 0.00 |
| Indicator 2 | Capacity of supported childcare or educational infrastructure, Measure Unit: лица, Base Value: 0.00 , Target amount: 750.00 , Reached amount: 500.00 |
| Indicator 3 | Representatives from marginalised groups, including roma benefiting from modernised social infrastructure, Measure Unit: лица, Base Value: 0.00 , Target amount: 120.00 , Reached amount: 100.00 |
| Total Project cost | 68 461.99 EUR |
| Grant | 68 461.99 EUR |
| Self amount | 0.00 EUR |
| Total actual amounts paid | 360 307.39 EUR |
| Percentage of EU co-financing | 85.00 % |
| None | |
|
Notes: 1 The quoted value represents the maximum amount of the imposed financial correction. Depending on the performance of the contract, the actual amount of the deducted financial correction may be lower. 2 A financial correction with a zero total value means that it has been canceled as a result of a court judgment. |
|
| Procedure 1 |
Subject to due process: Авторски надзор,
Estimated Amount: 5 112.92
|
| Procedure 2 |
Subject to due process: Одит,
Estimated Amount: 1 022.58
|
| Procedure 3 |
Subject to due process: Публичност,
Estimated Amount: 7 669.38
|
| Procedure 4 |
Subject to due process: СМР,
Estimated Amount: 869 196.20
|
| Procedure 5 |
Subject to due process: Строителен надзор,
Estimated Amount: 10 225.84
|
Notes:
All amounts are in euro (EUR) / 1 EUR = 1,95583 BGN